The following is a general timeline for our building process.
The intention of this page is to assist buyers with the sequence of events when building your Riptide Home. While no Riptide build is typical, many of the building stages are similar from one build to another, so we have a pretty good idea of how long it will take to construct your unique Riptide Home.
In no way does this represent definitive dates. Typically, our homes take ~180 days from land clearing.
The Design/Planning phase typically takes ~30 days prior to securing the build permit depending on jurisdiction, community Architectural Review requirements and schedule.
Design/Planning (30 Pre-Build Days)
Initial Meeting/Consultation/Price Overview
Preliminary Agreement/Good Faith Deposit Terms
Neighborhood/Lot Selection
Builder Review for Lot
Place Lot under Contract (If Applicable)
Pre-Design Meeting/Review of Concepts/Pricing
Design House Plans & Plot Plans
Formulate Specs/Selections for Final Plan
Prelim Survey Work for Tree walk
Super to Complete Initial Tree Walk
Complete Selections at Design Center
Complete Lot Orientation/Tree Walk
Complete Overview Prior to Contract
Execute Contract
Submit to ARC/HOA Committees for Approval
Permitting Process (Pre-Build Days)
Install all Signage and Permit Boxes
Determination of Septic/Sewer/Well/County Water
Update All Septic/Well Permits (If Applicable)
Pay All Sewer/Water Tap Fee’s (If Applicable)
Submit For Building Permit
Build Days 1-45
Clear Land
Foundation Completion (Depending on foundation type, Monolithic Slab, Raised Slab, Crawl Space, Pilings) - Footings, Block Work, Fill Foundation, Plumbing and Electrical in Slab, Concrete Flat Work,
Framing of House
Build Days 45-90
Drying In of House – House Wrap/Roof Felt
Window and Door installation
Roofing Installation
All Roughs Ins – HVAC, Plumbing, Electrical, Gas, Low Voltage (Security and Sound)
Client Rough Walk
Insulation Installation
Drywall Installation and Completion
Kitchen/Bath Cabinet Installation
Trim and Doors Installation
Siding Installation
Stone or Brick Installation (Applicable Areas)
Septic Installation/Sewer Installation
Build Days 90-130
Granite Installation
Painting of Interior of House
Garage Door Installation
Exterior Rails, Columns, Stick Work
Tile all Baths Laundry and Applicable Areas
Driveway Installation
Trim Out’s – Completion of all HVAC, Plumbing, Electrical, Gas, Low voltage Systems
Installation of Finish Flooring – Wood/Carpet
Final Trim Labor Interior and Exterior
Closet Shelving, Mirrors, Knobs
Construction Clean
Final Paint – Interior and Exterior
Landscape Installation and Completion
Build Days 130-175
Detailed Builder Punch out
Certificate of Occupancy
Final Touch Ups and Clean
First Client Walk
Client Punch Out Touch Ups
Final Interior and Exterior Clean
Final Client Walk
Closing